Jaycee Park Improvements

Jaycee Park Improvements

Tennis and Basketball Project


May 26 2022 - Connection to City Storm System


May 26 2022 - New Storm Pipe Installation

May 4 2022
May 4 2022

Jaycee Park Tennis & Basketball Courts

The tennis courts remain closed at this time due to the hazardous conditions, but the Park District is currently in the planning/permitting stage for the full replacement of the tennis and basketball courts. We anticipate permit drawings being completed and submitted to regulatory agencies at the end of June 2021. The permitting process can take several months, so construction will begin in Spring 2022. 

UPDATES:

May 27, 2022 - The storm sewer system is being installed this week. 

May 20, 2022 - The permit approval indicated some changes to the plans, and those changes were incorporated into the construction documents this week. Work is scheduled to resume on Monday with the installation of the storm sewer system. The project is on track to be completed by August. 

May 13, 2022 - The clearing and demolition phase of the project is completed, and the next step is installation of storm sewer.

May 4, 2022 - The project commenced today! Construction fencing was erected. This week the existing fencing, basketball goals and net posts will be demolated. The contractor will also grind the existing asphalt and begin sewer work. 

July 16, 2021 - SmithGroup, our project engineer for the tennis and basketball courts replacement, is developing the schematic drainage plan for the project site. During this process, it was determined that some key information on the City atlases and maps are missing data. The project team is coordinating with the City on this missing data. The project is expected to be out to bid in the fall/winter of 2021 and construction will begin in 2022.